BALL MILL/COAL MILL OVERHAUL SERVICES (PART 1: GEARBOX)

9tLLM9r.jpeg

Ball Mill/Coal Mill is one of the extremely important equipment in cement, thermal power, chemical plants, ... to help grind clinker, ore, coal and other materials. Due to often working in harsh environments, it is essential to organize overhauling to avoid serious failures in the future that affect production progress.

B2B International Company Ltd. provides an overhaul service package for Ball Mill/Coal Mill including maintenance - repair - alignment - restoration - replacement of spare parts by a team of experts, skilled and experienced technicians. Here are some of the services we offer..

I. GEARBOX

1. Position

- Position of gearbox in ball mill/coal mill system

EZvVbMo.jpeg 

2. Common problems:

+ Gearbox dirt, vibration and temperature do not meet standard quality due to long-time operation in harsh environments.

+ Gears and bearings are misaligned and broken.

+ Gear contact is misaligned.

+ Axial concentricity is deflected.

+ Coupling misaligned between gearbox and gear.

+ Coupling misaligned between gearbox and motor.

+ Bolts loosened during operation.

+ Oil seals, flanges, connecting pipes, etc. are leaking and damaged.

+ Oil pump problem

+ Etc.

3. Process of overhaul - repair - maintenance of ball mill/coal mill gearbox

- Step 1: Remove and take the gearbox to the repair area

6F7DU78.jpg 

- Step 2: Clean the gearbox cover - Remove the flange

O97w1yz.jpg

- Step 3: Check gear contact and backlash before disassembling

 Fa1XlHi.jpg 

- Step 4:

+ Remove the bearing from the input shaft - intermediate shaft - output shaft.

+ Heating the bearing, replace damaged bearings, replace damaged spare parts.

+ Clean all spare parts.

 XV2eH5n.jpg 

 jlYzljc.jpg 

- Step 5: Install the bearing for the input shaft - intermediate shaft – output shaft

 8kjCeRH.jpg

- Step 6: Check the gearbox cover

Oz0Mt2S.jpg  

Step 7: Check the gear contact and the backlash after installing

 7Jq8j6s.jpg 

 iKYquEL.jpg 

- Step 8: Reassemble the components into the gearbox

 uSE6J8i.jpg 

 wh9xy54.jpg 

 

- Step 9: Check again until the parameters that have met the requirements will be re-installed into the system for further operation.